entergy's indian point unit 3 nuclear power plant returned to service yesterday generating electricity, after a sixteen-day shutdown to replace a failed main electrical transformer. the unit had safely and automatically shut down when the transformer failed on may 9.
latest news
news > safety
indian point unit 3 back in service, generating electricity following transformer replacement
05/26/2015
news > safety
indian point unit 3 transformer liquid discharge into hudson estimated at approximately 3,000 gallons; hotline telephone available to report potential oil sightings
05/21/2015
entergy personnel continue working closely with the u.s. coast guard and the new york state department of environmental conservation to investigate and mitigate the environmental impact of dielectric fluid on the river following the may 9 transformer failure at indian point unit 3.
news > safety
entergy continues investigation of failed transformer, spilled dielectric fluid at indian point energy center
05/14/2015
entergy continues to investigate the cause of the failed transformer and subsequent spill of the transformer's dielectric fluid following the event which occurred on may 9. the failed transformer is located outdoors in the transformer yard and external to any buildings that contain radioactive materials.
news > safety
entergy leading response to monitor and mitigate potential impacts to hudson river following transformer failure at indian point energy center
05/13/2015
entergy continues to lead response and mitigation efforts following the may 9 transformer failure that led to the safe shutdown of indian point unit 3.