news release > entergy mississippi completes $37m service reliability project in warren county
entergy mississippi completes $37m service reliability project in warren county
07/21/2021
transmission circuit serves more than 4,000 customers, including ceres industrial park
jackson, mississippi – entergy mississippi recently completed a $37-million transmission upgrade that will improve service reliability to customers in the flowers area of warren county. the project involved the installation of transmission breakers on the beech grove-yazoo city-north vicksburg 115kv circuit. it began in november 2020 and is now in service.
highlights of the project include:
- constructing new and rebuilding portions of transmission lines using steel structures, upgraded conductor and fiber communications;
- constructing new and rebuilding portions of distribution lines using standard structures and upgraded conductor;
- expanding capacity at the flowers substation from 8 mw to 50 mw and upgrading it, including hardening it against animal intrusions, and
- rebuilding the river crossing at big black river.
“the flowers reliability improvement project continues to demonstrate entergy mississippi’s commitment to placing new capital projects in service to support the needs of our customers,” said haley fisackerly, entergy mississippi president and ceo. “between 2018 and 2020, entergy mississippi placed more than $416 million in new transmission capital projects in service.
“in 2021, we plan to invest $120 million to continue to upgrade and modernize our transmission system.”
the transmission circuit serves about 4,000 warren county customers along 58 miles of transmission line. these customers include seven companies in the ceres industrial park that employ some 1,000 people.
“the ceres industrial park, which is served from entergy’s flowers’ substation, now has three independent transmission sources, so our customers there should see a dramatic increase in reliability,” said ed gardner, entergy mississippi director of business and 2022年世界杯比分. “reliability of electric service is key to industry locating in an area.”
“ceres is also home to three entergy qualified sites,” he added. “this investment in reliability will increase our ability to market, locate and grow companies in the park.”
decreased outages not only cut down on the down time industrial customers experience, but also on the significant time it takes to restart heavy machinery and bring employees back on the job. outages can also cause sensitive industrial equipment to fail, creating more down time and financial costs while the equipment is repaired or replaced.
the flowers project complements another major transmission project that went into service in march. the $31-million mill street substation provides a strong, new source into the city of jackson and allows entergy to support economic growth and continue to provide reliable service at reasonable prices. the substation and supporting infrastructure upgrades provide an extra source of power into jackson and supports the expanding fondren community and jackson medical corridor, including ummc and children’s hospital.
entergy mississippi, inc. provides electricity to approximately 456,000 customers in 45 counties. entergy mississippi is a subsidiary of 沙特vs墨西哥让球, an integrated energy company engaged in electric power production, transmission and retail distribution operations. entergy delivers electricity to 3 million utility customers in arkansas, louisiana, mississippi and texas. entergy owns and operates one of the cleanest large-scale u.s. power generating fleets with approximately 30,000 megawatts of electric generating capacity, including 7,000 megawatts of nuclear power. headquartered in new orleans, louisiana, entergy has annual revenues of $10 billion and more than 13,000 employees. learn more at entergy.com and follow @entergy on social media.